Clark County has recently updated their permitting process to make it more efficient. These changes are for Rural Tax Lots only. The information learned from these improvements will be used in future process improvements. View full document here.
Highlights: REVISED PERMIT PROCESS:
1) Preapplication meeting conducted with applicant.
2) DAY 1-Completed application submitted
No deferrals and all required documentation complete,
3) DAY 2-10 Review Process: Single round of reviews - Plan mark-up and approval with conditions.
4) DAY 12-14 Applicant accepts review corrections/conditions, conditional; permit issued, applicant submits revised for approval and inspector field verifies corrections.
To view the full draft of pre-application meeting process, click
here.